Li Zongqing, Yan Xiuliang, Chen Yongming, Zhu Huangang, Cao Qiang. Development and Test of Three-Parameter Automatic Pressure Control Drilling System[J]. Petroleum Drilling Techniques, 2012, 40(6): 99-103. DOI: 10.3969/j.issn.1001-0890.2012.06.021
Citation: Li Zongqing, Yan Xiuliang, Chen Yongming, Zhu Huangang, Cao Qiang. Development and Test of Three-Parameter Automatic Pressure Control Drilling System[J]. Petroleum Drilling Techniques, 2012, 40(6): 99-103. DOI: 10.3969/j.issn.1001-0890.2012.06.021

Development and Test of Three-Parameter Automatic Pressure Control Drilling System

More Information
  • Received Date: April 23, 2012
  • Revised Date: October 07, 2012
  • In order to solve the problems including circulation loss,well kick,differential pressure sticking,especially simultaneous kick and loss in narrow density window formation,encountered in the process of conventional drilling related to wellbore pressure,three-parameter automatic pressure control drilling system has been developed on the basis of studying the current technologies at home and abroad.According to the U tube principle,the system gathers drilling parameters including casing pressure,drillpipe pressure and flow rate,etc,and controls these parameters jointly by choke valve automatic control,realizing seamless control shift,the field experiment was carried out in full-scale simulated well.During the control of drillpipe pressure or casing pressure,the entire control process was steady,no overshoot,oscillation and divergence occurred,and pressure control error was no more than 0.2 MPa.In the case of kick and loss of circulation,sensitive flow monitoring and timely control can restrict the volume of overflow and leakage to less than 800 liters total.The test results show the pressure control technique of taking casing pressure,drillpipe pressure and flow rate as control target overcomes the shortage in casing pressure control drilling,offering a better solution for pressure control drilling.
  • [1]
    朱丽华.控制压力钻井技术[J].钻采工艺,2008,31(3):4. Zhu Lihua.Managed pressure drilling technology[J].Drilling Production Technology,2008,31(3):4.
    [2]
    Hannegan D M.Managed pressure drilling in marine environments:case studies[R].SPE/IADC 92600,2005.
    [3]
    Hannegan D,Todd R J,Pritchard D M,et al.MPD:uniquely applicable to methane hydrate deilling[R].SPE/IADC 91560,2004.
    [4]
    Santos H,Leuchtenberg C,Shayegi S.Micro-flux control:the next generation in drilling process[R].SPE 81183,2003.
    [5]
    Santos H,Catak E,Kinder J,et al.First field applications of mi-croflux control show very positive surprises[R].IADC/SPE 108333,2007.
    [6]
    Fredericks P D,Reitsma D.MPD automation addresses drilling challenges in conventional,unconventional resources[J].Drilling Contractors, 2006,62(6):46-49.
    [7]
    McMillan S,An W H,Zhang Y M,et al.Overcoming drilling challenges in northwest China using an innovative MPD technique[R].SPE/IADC 130317,2010.
    [8]
    屈俊波,陈平,马天寿,等.精确监测井底溢流的井下微流量装置设计与试验[J].石油钻探技术,2012,40(5):106-110. Qu Junbo,Chen Ping,Ma Tianshou,et al.Design and test of down-hole micro-flow device for monitoring over flow[J].Petroleum Drilling Technigues,2012,40(5):106-110.
    [9]
    李群生,朱礼平,李果,等.基于井下流量测量的微流量控制系统[J].石油钻探技术,2012,40(3):23-27. Li Qunsheng,Zhu Liping,Li Guo,et al. Micro-flow control systen based on down hole flow measurement[J].Petroleum Drilling Techniques,2012,40(3):23-27.
    [10]
    集团公司井控培训教材编写组.钻井井控工艺技术[M].东营:中国石油大学出版社,2008:92-93. Conglomerate Well Control Teaching Material Redaction Group.Well control technology[M].Dongying:China University of Petroleum Press,2008:92-93.
  • Related Articles

    [1]YANG Liqiang. Development and Application of Intelligent Control Devices for BOPs[J]. Petroleum Drilling Techniques, 2024, 52(5): 138-144. DOI: 10.11911/syztjs.2024088
    [2]XU Youfu, ZHANG Zhongqiang, FANG Hualiang. Well Control Technologies for HTHP Gas Wells in the C Block of the South China Sea[J]. Petroleum Drilling Techniques, 2017, 45(4): 21-26. DOI: 10.11911/syztjs.201704004
    [3]NIU Xinming, ZHANG Jinshuang, ZHOU Haobo. Technological Challenges and Countermeasures in Well Control of Ultra-Deep, Ultra-High Temperature and Ultra-High Pressure Oil and Gas Wells[J]. Petroleum Drilling Techniques, 2017, 45(4): 1-7. DOI: 10.11911/syztjs.201704001
    [4]Jin Yequan, Hu Man, Wu Qian, Ji Yongqiang. Analysis of Deepwater BOP Failure in the Macondo Well Accident[J]. Petroleum Drilling Techniques, 2014, 42(4): 53-58. DOI: 10.3969/j.issn.1001-0890.2014.04.010
    [5]Zhang Tao, Li Jun, Liu Gonghui, Xi Yan, Sun Lisheng. Pressure Regulation Characteristics of Automatic Choke Manifold in Managed Pressure Drilling[J]. Petroleum Drilling Techniques, 2014, 42(2): 18-22. DOI: 10.3969/j.issn.1001-0890.2014.02.004
    [6]Zhang Guilin, Chen Zhining. Problems Analysis and Proposed Amendments for Current Drilling Well Control Standards[J]. Petroleum Drilling Techniques, 2014, 42(1): 7-13. DOI: 10.3969/j.issn.1001-0890.2014.01.002
    [7]Sun Lianwei, Guan Zhichuan, Liang Haiming, Jiang Mengna. Effects of Casing Program Change and Liner Tieback on Well Control[J]. Petroleum Drilling Techniques, 2013, 41(6): 34-39. DOI: 10.3969/j.issn.1001-0890.2013.06.007
    [8]Cao Shijing. Discussion on Configuration of Subsea BOP Stack and Its Control System in Ultra-Deep Water[J]. Petroleum Drilling Techniques, 2012, 40(5): 115-118. DOI: 10.3969/j.issn.1001-0890.2012.05.025
    [9]Zhang Xingquan, Li Xiangfang, Ren Meipeng, Xu Darong. Research on the Well Control Techniques of Bullheading[J]. Petroleum Drilling Techniques, 2012, 40(3): 62-66. DOI: 10.3969/j.issn.1001-0890.2012.03.013
    [10]Chu Daoyu. Well Control Technology in Deepwater Well[J]. Petroleum Drilling Techniques, 2012, 40(1): 52-57. DOI: 10.3969/j.issn.1001-0890.2012.01.011

Catalog

    Article Metrics

    Article views (3212) PDF downloads (3286) Cited by()
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return