ZHOU Bo, YANG Jin, ZHOU Jianliang, LIU Zhengli, YANG Jiangang. A Jetting Flow Rate Design Method for Conductor Installation through Jetting in Deepwater Drilling[J]. Petroleum Drilling Techniques, 2016, 44(3): 21-26. DOI: 10.11911/syztjs.201603004
Citation: ZHOU Bo, YANG Jin, ZHOU Jianliang, LIU Zhengli, YANG Jiangang. A Jetting Flow Rate Design Method for Conductor Installation through Jetting in Deepwater Drilling[J]. Petroleum Drilling Techniques, 2016, 44(3): 21-26. DOI: 10.11911/syztjs.201603004

A Jetting Flow Rate Design Method for Conductor Installation through Jetting in Deepwater Drilling

More Information
  • Received Date: July 13, 2015
  • Revised Date: February 25, 2016
  • When conductors are installed in deepwater drilling through jetting, it is necessary to design jetting flow rate appropriately based seabed parameters so as to guarantee the proper installation of conductors and rational recovery time of conductor capacity. A computation model of minimum jetting flow rate for rock breaking was established according to the submerged water jet theory and the unconsolidated seabed failure criteria. Then a pilot simulation test was carried out on conductor (φ339.7 mm) installation by jetting to analyze the influential rules of jetting flow rate on seabed breaking and surface conductor capacity. It is shown that the lowering velocity of conductors would be slow when jetting flow rate is less than a minimum certain value. On the other hand, the lowering velocity of conductors would increase quickly with the increasing of the jetting flow rate. The conductor bearing capacity decreases exponentially with the increasing of the jetting flow rate and reaches the lowest when jetting flow rate is over 1.2 times of the minimum value. Based on the calculation model and simulation of minimum jetting flow rate, the jetting flow rate design method is established under the constraint of hydraulic seabed breaking capacity and conductor bearing capacity. It has been applied in 22 deepwater wells in the South China Sea and the installation efficiency of conductors from jetting is increased and conductor stability is guaranteed.
  • [1]
    汪顺文,杨进,严德,等.深水表层导管喷射钻进机理研究[J].石油天然气学报,2012,34(8):157-160. WANG Shunwen,YANG Jin,YAN De,et al.Research of jetting drilling mechanism of surface conductor in deepwater[J].Journal of Oil and Gas Technology,2012,34(8):157-160.
    [2]
    JEANJEAN P.Innovative design method for deepwater surface casings[R].SPE 77357,2002.
    [3]
    徐荣强,陈建兵,刘正礼,等.喷射导管技术在深水钻井作业中的应用[J].石油钻探技术,2007,35(3):19-22. XU Rongqiang,CHEN Jianbing,LIU Zhengli,et al.The appliation of jetting technology in deepwater drilling[J].Petroleum Drilling Techniques,2007,35(3):19-22.
    [4]
    罗俊丰,杨进,严德,等.深水钻井表层导管喷射安全等候时间窗口设计[J].石油机械,2014,42(4):53-56. LUO Junfeng,YANG Jin,YAN De,et al.Design of the safety waiting conductor jet in time window for surface subsea drilling[J].China Petroleum Machinery,2014,42(4):53-56.
    [5]
    周波,杨进,刘正礼,等.深水钻井表层导管静置时间窗口设计[J].石油勘探与开发,2014,41(2):234-238. ZHOU Bo,YANG Jin,LIU Zhengli,et al.Design of structure casing soaking time in deepwater drilling[J].Petroleum Exploration and Development,2014,41(2):234-238.
    [6]
    柯珂,张辉,周宇阳,等.深水钻井喷射下导管模拟试验装置的研制[J].石油钻探技术,2015,43(2):33-37. KE Ke,ZHANG Hui,ZHOU Yuyang,et al.The development of testing simulators for conductor jets running in deepwater drilling[J].Petroleum Drilling Techniques,2015,43(2):33-37.
    [7]
    ZHOU Bo,YANG Jin,XU Yunjin,et al.Experimental research on structural casing soaking time in deepwater drilling[R].SPE 170317,2014.
    [8]
    AKERS T J.Jetting of structural casing in deepwater environments:job design and operational practices[J].SPE Drilling Completion,2008,23(1):29-40.
    [9]
    BECK R D,JACKSON C W,HAMILTON T K.Reliable deepwater structural casing installation using controlled jetting[R].SPE 22542,1991.
    [10]
    王磊,张辉,周宇阳,等.深水钻井喷射下导管水力参数优化设计方法[J].石油钻探技术,2015,43(2):19-24. WANG Lei,ZHANG Hui,ZHOU Yuyang,et al.Optimal design of hydraulic parameters for conductor jetting in deepwater drilling[J].Petroleum Drilling Techniques,2015,43(2):19-24.
    [11]
    杜嘉鸿,张士旭.高压喷射注浆技术应用现状及新进展[J].探矿工程(岩土钻掘工程),1995,22(4):4-6,10. DU Jiahong,ZHANG Shixu.Present application and new advances of high pressure jet grouting technique[J].Exploration Engineering(Rock Soil Drilling and Tunneling),1995,22(4):4-6,10.
    [12]
    廖华林,李根生,易灿.水射流作用下岩石破碎理论研究进展[J].金属矿山,2005(7):1-5,66. LIAO Hualin,LI Gensheng,YI Can.Advance in study on theory of rock breaking under water jet impact[J].Metal Mine,2005(7):1-5,66.
    [13]
    马飞,宋志辉.水射流动力特性及破土机理[J].北京科技大学学报,2006,28(5):413-416. MA Fei,SONG Zhihui.Dynamic property and breaking soil mechanism of water jet[J].Journal of University of Science and Technology Beijing,2006,28(5):413-416.
    [14]
    周建良.深水表层导管喷射钻进过程中钻井液排量优化研究[J].中国海上油气,2012,24(4):50-52. ZHOU Jianliang.Research on the optimization of delivery capacity during jetting drilling of surface conduct in deep water[J].China Offshore Oil and Gas,2012,24(4):50-52.
  • Cited by

    Periodical cited type(10)

    1. 傅超,杨进,刘华清,殷启帅,王磊,胡志强. 多维度深水浅层建井方式优选方法研究. 石油钻探技术. 2024(03): 40-46 . 本站查看
    2. 杨进,傅超,刘书杰,李中,张伟国,刘正礼. 中国深水钻井关键技术与装备现状及展望. 世界石油工业. 2024(04): 69-80 .
    3. 徐东升,杨进,樊建春,李炎军,宋宇,严德. 深水吸力桩承载力学特性及稳定性分析. 石油机械. 2023(06): 57-65 .
    4. 张来斌,谢仁军,殷启帅. 深水油气开采风险评估及安全控制技术进展与发展建议. 石油钻探技术. 2023(04): 55-65 . 本站查看
    5. 杨进,李文龙,胡志强,殷启帅,李舒展. 深水钻井水下井口稳定性研究进展. 中国海上油气. 2020(04): 124-130 .
    6. 刘正礼,严德. 南海东部荔湾22–1–1超深水井钻井关键技术. 石油钻探技术. 2019(01): 13-19 . 本站查看
    7. 王腾,宋斌. 黏土中射流破土机理的研究. 水动力学研究与进展(A辑). 2018(03): 337-343 .
    8. 海存斌. 大型矿山钻探钻井技术研究. 中国金属通报. 2018(06): 203+205 .
    9. 许定江,练章华,张强,林铁军. 深水钻完井工程设计要点分析. 断块油气田. 2017(01): 131-136 .
    10. 刘和兴,方满宗,刘智勤,徐一龙,孟文波. 南海西部陵水区块超深水井喷射下导管技术. 石油钻探技术. 2017(01): 10-16 . 本站查看

    Other cited types(8)

Catalog

    Article Metrics

    Article views (2517) PDF downloads (3048) Cited by(18)
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return